Progress - Time Line and Milestones
 
 

Core Activity

Tasks Target Status Comments
1 Establish Organization

a) Register with State

03/01/05 Done Complete

b) Register 501(c)(3) with IRS

03/15/05 Done Complete
c) Appoint Board and Officers 03/15/05 Done Complete
d) Define Vision and Mission 03/01/05 Done Complete
e) Define Project Scope 03/01/05 Done Phase 1 50 homes
 

Core Activity

Tasks Target Status Comments
2 Funding

a) Over All Goals

05/31/05 WIP $590,000

b) Phase One

04/30/05 WIP $250,000
c) Phase Two 05/31/05 WIP $340,000
d) Strategy 03/31/05 WIP Individual $55,000
      Corporate $225,000
Institutions $310,000
 

Core Activity

Tasks Target Status Comments
3 Land Procurement

a) Phase One

03/31/05 Done 30- 50 Complete

b) Phase Two

03/15/05 Done 50-100 Complete
c) Allotment from SL Govt. 03/23/05 Done Phase one Complete
d) Commitment for Infrastructure 03/23/05 Done Phase one Complete
e) Plan B? 03/01/05 Done If SL Govt. fails?
 

Core Activity

Tasks Target Status Comments
4 Construction

a) Select Plans Review Options

04/15/05 Done By the Board

b) Select Contractor

04/30/05 Done Govt. Approved
c) Select Supervisor 04/30/05 Done Qualifications to check
d) Construction Launch 05/01/05 Done Phase 1
e) Construction Completion 08/30/05 Done Phase 2 to be defined
 

Core Activity

Tasks Target Status Comments
5 Selection of Recipients

a) Define Criteria

05/01/05 WIP Tsunami Survivor etc.

b) Define expectations

05/31/05 WIP Recipient and MnSLFF
c) Needs Assessment 05/31/05 WIP Livelihood - Data
d) Ownership Covenants 06/30/05 WIP Local Law Compliance
e)  Naming Protocols 06/30/05 WIP Local Law
f) Move In 09/01/05 Phase 1 Ends.